A little maths help would be nice please!!!
#1
A little maths help would be nice please!!!
My head is going to explode trying to work out a proposed temporary change of hours at work, I'm hoping someone can please check my maths or maybe point me right if possible please
I currently work 40 hours per week, but for a period of time my company would like me to work different hours.
The dates are: July 1st until September 16th.
My shifts would be "6 on" and then "4 off". The "6 on" equals 58 hours.
I work out that over that same period (11 weeks I make it), I would normally do 11 x 40hr weeks, so 440 hours in total.
But I work out, that starting from July the 1st, "6 on", I would do 8 x 58 hour shifts over the 11 weeks, so 464 hours in total.
Am I correct? My management seem to think it's less than the 440 hours I do now!!!!!
I think I've gone into meltdown and cannot see the light
Any help greatly appreciated so I can fight my corner
Cliff
I currently work 40 hours per week, but for a period of time my company would like me to work different hours.
The dates are: July 1st until September 16th.
My shifts would be "6 on" and then "4 off". The "6 on" equals 58 hours.
I work out that over that same period (11 weeks I make it), I would normally do 11 x 40hr weeks, so 440 hours in total.
But I work out, that starting from July the 1st, "6 on", I would do 8 x 58 hour shifts over the 11 weeks, so 464 hours in total.
Am I correct? My management seem to think it's less than the 440 hours I do now!!!!!
I think I've gone into meltdown and cannot see the light
Any help greatly appreciated so I can fight my corner
Cliff
#2
Scooby Senior
Join Date: Mar 2003
Location: Next door to the WiFi connection
Posts: 16,293
Likes: 0
Received 0 Likes
on
0 Posts
Theres 77 days between the 1st of July and the 16th of Sept which divided by the 11 weeks makes 7 full weeks work doing 58 hours at a time each instead of 11 weeks of 40 hours work.
Basically your work is right, you will be doing 406 hours in total over the period on your 6 on 4 off scheme.
Good luck and I take no responsibility for my math being wrong lol
Basically your work is right, you will be doing 406 hours in total over the period on your 6 on 4 off scheme.
Good luck and I take no responsibility for my math being wrong lol
#4
I think you're right that you will do 8 six day shifts between 1 July and 16 Sept if the first starts on 1 July. The last shift will finish on 15 September, so if you switch back to normal working on 17 September you will only get one day of the last four day off period. If each six day shift is 58 hours then I agree this is 464 hours.
Where does the 58 hours per shift come from? If you are working six 8 hour days that would only be 48 hours for each shift, which would mean you are only working 384 hours. 58 hours would mean you are working 11.6 hours a day, which doesn't seem to make sense.
Where does the 58 hours per shift come from? If you are working six 8 hour days that would only be 48 hours for each shift, which would mean you are only working 384 hours. 58 hours would mean you are working 11.6 hours a day, which doesn't seem to make sense.
Trending Topics
#8
I think you're right that you will do 8 six day shifts between 1 July and 16 Sept if the first starts on 1 July. The last shift will finish on 15 September, so if you switch back to normal working on 17 September you will only get one day of the last four day off period. If each six day shift is 58 hours then I agree this is 464 hours.
Where does the 58 hours per shift come from? If you are working six 8 hour days that would only be 48 hours for each shift, which would mean you are only working 384 hours. 58 hours would mean you are working 11.6 hours a day, which doesn't seem to make sense.
Where does the 58 hours per shift come from? If you are working six 8 hour days that would only be 48 hours for each shift, which would mean you are only working 384 hours. 58 hours would mean you are working 11.6 hours a day, which doesn't seem to make sense.
2 x early shifts at 10 hours each!!! (20 hours)
2 x late shifts at 10 hours each!! (20 hours)
2 x night shifts at 9 hours each!! (18 hours)
#10
Scooby Regular
iTrader: (5)
Join Date: Nov 2011
Location: North wales side of Chester
Posts: 1,076
Likes: 0
Received 0 Likes
on
0 Posts
Have you taken into account weekends?
I mean as your doing so many on then 4 off, as they progress through the weeks, when you get to weekends, some of your days will fall in one week and some will fall in the next week, even though your working that many days, they would be split across 2 weeks, this matters if your weekly paid!
I mean as your doing so many on then 4 off, as they progress through the weeks, when you get to weekends, some of your days will fall in one week and some will fall in the next week, even though your working that many days, they would be split across 2 weeks, this matters if your weekly paid!
#12
Have you taken into account weekends?
I mean as your doing so many on then 4 off, as they progress through the weeks, when you get to weekends, some of your days will fall in one week and some will fall in the next week, even though your working that many days, they would be split across 2 weeks, this matters if your weekly paid!
I mean as your doing so many on then 4 off, as they progress through the weeks, when you get to weekends, some of your days will fall in one week and some will fall in the next week, even though your working that many days, they would be split across 2 weeks, this matters if your weekly paid!
#13
Scooby Senior
Join Date: Mar 2003
Location: Next door to the WiFi connection
Posts: 16,293
Likes: 0
Received 0 Likes
on
0 Posts
I suppose if you work on 10 day week (6 on 4 off) and 77 days over the period. making 7.7*58 hours = 446 working hours. But thats presuming the who 6 days on and 4 days off would work exactly over the 77 days. which is doesnt haha
Last edited by davegtt; 17 April 2012 at 07:25 PM.
#14
Scooby Regular
iTrader: (11)
For the first 70 days of the period, you'd have worked an extra 6 hours doing the 6 on 4 off than your normal 40 hour week, so it would all depend what your shifts are for the last 7 days, and/or when your first day back at work on normal shifts would be after the 14th (and up to a point, also whether you normally work weekends, since 1st July is a Sunday).
If you were working a 6 day shift up until the 14th, then expected back at work on Monday 17th, you'd end up having worked an extra 24 hours compared with a normal mon-fri 40 hour setup. If you worked a 6 day shift finishing on the 14th and then you didn't go back until the 19th, which is the date you should go back if you did 8 full cycles of the 6-on 4-off setup, you'd end up having worked just an extra 8 hours.
Sums as follows:
1st July to 8 September:
6-on, 4-off=406 hours
40-hour wk= 400 hours
9th September to 21st:
6-on, 4-off, due-back date of 17th=58+40
6-on, 4-off, due-back date of 19th=58+24
40 hour weeks=80
So, from 1st July to 21st September:
6-on, 4-off, due-back date of 17th=406+58+40=504
6-on, 4-off, due-back date of 19th=406+58+24=488
40 hour, mon-fri weeks right through=400+80=480
If you were working a 6 day shift up until the 14th, then expected back at work on Monday 17th, you'd end up having worked an extra 24 hours compared with a normal mon-fri 40 hour setup. If you worked a 6 day shift finishing on the 14th and then you didn't go back until the 19th, which is the date you should go back if you did 8 full cycles of the 6-on 4-off setup, you'd end up having worked just an extra 8 hours.
Sums as follows:
1st July to 8 September:
6-on, 4-off=406 hours
40-hour wk= 400 hours
9th September to 21st:
6-on, 4-off, due-back date of 17th=58+40
6-on, 4-off, due-back date of 19th=58+24
40 hour weeks=80
So, from 1st July to 21st September:
6-on, 4-off, due-back date of 17th=406+58+40=504
6-on, 4-off, due-back date of 19th=406+58+24=488
40 hour, mon-fri weeks right through=400+80=480
#16
I think your calculations are right. You probably need to find out how your bosses are working it out and show them where they are going wrong. I suspect they have done a simple averaging calculation based on you working 58 hours every 10 day cycle and then multiplied that by 7.7, which as davegtt pointed out gives 446.6 hours. That isn't right though because you will work six of the last seven days of the 77 day period.
#17
I think your calculations are right. You probably need to find out how your bosses are working it out and show them where they are going wrong. I suspect they have done a simple averaging calculation based on you working 58 hours every 10 day cycle and then multiplied that by 7.7, which as davegtt pointed out gives 446.6 hours. That isn't right though because you will work six of the last seven days of the 77 day period.
#18
The other thing to consinder is holidays are you are now working in effect a 10 day week ie your normal working week to get 14 days off you would need 10 days holiday now you only need 6 days to get a full 14 days off so your days would need cut pro rata. Not a problem if your not taking time off.
Thread
Thread Starter
Forum
Replies
Last Post
Mattybr5@MB Developments
Full Cars Breaking For Spares
28
28 December 2015 11:07 PM
Mattybr5@MB Developments
Full Cars Breaking For Spares
12
18 November 2015 07:03 AM