Microsoft Project Help
#1
Microsoft Project Help
Is it possible to insert a one-off task into non-working timeslot?
ie. I have a huge programme with many parallel activities. There are one or two tasks which I would like to happen during a weekend. In making that weekend "working time", all subsequent tasks which are planned for Mon/Tue the following week jump back 2 days (as they are linked) and use the weekend as working time also.
I don't want this to happen..
Rather than altering links to +2days (to miss weekends) is there an easier alternative?
Hope that explains ok
Thanks
Nick
ie. I have a huge programme with many parallel activities. There are one or two tasks which I would like to happen during a weekend. In making that weekend "working time", all subsequent tasks which are planned for Mon/Tue the following week jump back 2 days (as they are linked) and use the weekend as working time also.
I don't want this to happen..
Rather than altering links to +2days (to miss weekends) is there an easier alternative?
Hope that explains ok
Thanks
Nick
Thread
Thread Starter
Forum
Replies
Last Post
Mattybr5@MB Developments
Full Cars Breaking For Spares
28
28 December 2015 11:07 PM
Mattybr5@MB Developments
Full Cars Breaking For Spares
12
18 November 2015 07:03 AM
Phil3822
General Technical
0
30 September 2015 06:29 PM