Microsoft Project question
#1
Microsoft Project question
Does anyone know how to split a task into segments on Project. eg: 3 days on, 4 days off, 3 days on etc?
I'm sure it's possible as I've seen task bars split with dotted lines in between.
Anybody?
Nick
I'm sure it's possible as I've seen task bars split with dotted lines in between.
Anybody?
Nick
#2
Scooby Regular
Join Date: Mar 2001
Location: Derbyshire
Posts: 4,496
Likes: 0
Received 0 Likes
on
0 Posts
I know you can right click on a task and select split (or at least I think you can), and manually separate the sections, but not sure on if you can specify an algorithmic way.