Microsoft Project - Help!
Hi
I have 2 problems.
The 1st is that when starting a new project, if I put a duration of 1 day in, the bar show 3 days. I guess my template is confirgured wrong?
The 2nd problem is that I used an existing programme to overcome problem 1. I've now found that when printing, the bars on the timeline do not show..
Nobody in my company appears to be an expert on Project, can anyone help?
:
Thanks
Nick
I have 2 problems.
The 1st is that when starting a new project, if I put a duration of 1 day in, the bar show 3 days. I guess my template is confirgured wrong?
The 2nd problem is that I used an existing programme to overcome problem 1. I've now found that when printing, the bars on the timeline do not show..
Nobody in my company appears to be an expert on Project, can anyone help?
:Thanks
Nick
Scooby Regular
iTrader: (13)
Joined: Jan 2001
Posts: 4,997
Likes: 0
From: Midlands - between notts and derby !
Hi
I have 2 problems.
The 1st is that when starting a new project, if I put a duration of 1 day in, the bar show 3 days. I guess my template is confirgured wrong?
The 2nd problem is that I used an existing programme to overcome problem 1. I've now found that when printing, the bars on the timeline do not show..
Nobody in my company appears to be an expert on Project, can anyone help?
:
Thanks
Nick
I have 2 problems.
The 1st is that when starting a new project, if I put a duration of 1 day in, the bar show 3 days. I guess my template is confirgured wrong?
The 2nd problem is that I used an existing programme to overcome problem 1. I've now found that when printing, the bars on the timeline do not show..
Nobody in my company appears to be an expert on Project, can anyone help?
:Thanks
Nick
2nd problem -- does the timeline section show at all either on the screen or on the print ... if you add a milestone (duration 0 days) does the black diamond show on the screen or print
DD
Thanks for your help. Yes resourcing was set wrong!
I managed to sort problem 2 out - as I had based a new workbook on a 2yr old programme, the start date was set to Jan 07, therefore it was only printing what it could see in the "2007" window.
Doh.
Thanks again.
Nick
Thanks for your help. Yes resourcing was set wrong!
I managed to sort problem 2 out - as I had based a new workbook on a 2yr old programme, the start date was set to Jan 07, therefore it was only printing what it could see in the "2007" window.
Doh.
Thanks again.
Nick
Thread
Thread Starter
Forum
Replies
Last Post
Mattybr5@MB Developments
Full Cars Breaking For Spares
28
Dec 28, 2015 11:07 PM
Mattybr5@MB Developments
Full Cars Breaking For Spares
12
Nov 18, 2015 07:03 AM
Phil3822
General Technical
0
Sep 30, 2015 06:29 PM